Apr 14:Ministry of Power has sought an Expression of Interest (EOI) for setting up a manufacturing zone on a pilot basis for the Power & Renewable Energy Sector. The Ministry had earlier issued orders conveying the implementation of a Scheme for Setting up a Manufacturing Zone for the Power and Renewable sector on a pilot basis with a budgetary outlay of Rs.400 crore over a period of five years.
This is Central Sector Scheme and the duration of the Scheme is five years from FY 2022-23 to FY 2026-27. The last date for submission of an Expression of Interest is 8th June 2022.
Brief description of the EOI Process:
EOI Process Authority has adopted a single-stage EOI Process for the selection of the Successful Proposer. Each Proposer is required to submit a single Proposal. All Proposals are required to be prepared and submitted in accordance with the terms of this EOI on or before the Proposal Due Date. Any queries or requests for additional information relating to this EOI shall be submitted to EOI Process Authority in accordance. EOI Process Authority shall endeavor to adhere to the following EOI Schedule:
Sl. | Event | Date and Time |
1. | Notification to Proposers | Wednesday, April 13, 2022 |
2. | Pre-EOI Meeting | Wednesday, April 27, 2022, at 11:00 AM |
3. | Last date of submission of queries or information required by Proposers | Wednesday, May 4, 2022, at 04:00 PM |
4. | Issue of clarifications, addendum, or revised EOI | Wednesday, May 11, 2022, at 04:00 PM |
5. | Proposal Due Date | Wednesday, June 8, 2022, at 04:00 PM |